California Reserve Upgrade

Project Overview

We are excited to let everyone know that the upgrade of California Reserve will start very soon!

Works are expected to be completed February/March 2022 and will deliver a much improved park for the community to enjoy.

A huge thank you to community members who provided input into the concept design earlier in the year. A summary of feedback received during the consultation period and response to issues raised is available from the Document Library to the right.

This project has been fully funded by the Australian Government as part of its Infrastructure Investment Program Stimulus.

Construction commencing

We are excited to let everyone know that the upgrade of California Reserve will start very soon!

California Reserve is located next to shops, bus stop and pedestrian trail.  It has basketball hoops, irrigated grass, signage and a playspace which has come to the end of its life.  It also has mature trees which provide shade and habitat.  The upgrade of this reserve will create a welcoming neighbourhood reserve in an existing community destination.

The upgrade will include:

  • New play space including all-abilities equipment and nature play
  • A loop trail around the reserve 
  • Fitness equipment
  • Shelters, picnic tables and BBQs
  • Public lighting and drinking fountain
  • Community Consultation

    19 April -  12 May 2021

  • Review of community feedback

    May 2021

  • Detailed design and engineering

    May - July 2021

  • Tender and procurement of construction contractors

    July - August 2021

  • Construction

    October/November 2021 - February/March 2022

    Note that times are subject to change

  • Community opening/launch event

    Date to be confirmed